Input type: DC input, positive common end.
Input points: 8 points.
Enter the response time: 0.2ms below, below 1.5ms, 5ms below, 10ms the following.
Rated input voltage / current: DC24V/7mA.
Output form: transistor output, leakage type.
Output points: 8 points.
OFF leakage current: 0.1mA.
Output protection function: No .
Rated load voltage / current: DC24V/0 MR-JE-100B. 5A.
External connection: 3 line /2 line type
MR-JE-100B
According to the external connection mode and the external equipment input and output specifications,
Choose from a rich product lineup.
Finger protection through the upper part of the terminal,
The human body will not be exposed to live parts,
Therefore, the terminal station type remote I/O module can be directly mounted to the machine tool MR-JE-100B. MITSUBISHI inverter FR-E720 series.
Voltage level: 3 phase 200V.
Frequency converter capacity: 1.5KW.
In order to ensure the reliability of production, all production machinery in the design of power with drive, there is a certain amount of surplus.
When the motor can not run under full load, in addition to meet the requirements of power driven,
The surplus torque increases the active power consumption, resulting in the waste of electric energy MR-JE-100B.
Speed control method of fan and pump equipment traditional by regulating the entrance or exit of the baffle, valve opening to regulate air flow and water flow
, the input power is large, and a large amount of energy consumption in the baffle, the valve in the process of closure.
When using variable frequency control, if the flow rate is reduced, the speed of the pump or fan can be reduced to meet the requirements. DC input points: 4 points.
Input voltage and current: 7mA, DC24V.
Input response time: 10ms.
4 point /1 a public side.
Positive pole sharing.
Output points: 4 points.
Output voltage and current: DC24V.
Output response time: 2ms.
4 point /1 a public side.
Output form: transistor output, leakage type.
24 point terminal station.
MITSUBISHI PLC protection and chain procedures.
Protection and chain is an indispensable part of the program, must be carefully considered.
It can avoid the control logic confusion caused by illegal operations.
MITSUBISHI PLC initialization procedure. After MITSUBISHI PLC on power, the general need to do some of the initial operation,
In order to start making necessary preparations, to avoid the wrong operation of the system.
The main contents of the initialization program are: to some data area, counter and so on,
Data needed to restore some of the data area,
Set or reset some relays,
For some initial staate display, etc MR-JE-100B..
MITSUBIISHI PLC program simulation debugging
The basic idea of program simulation debugging is,
In order to facilitate the form of simulation to generate the actual state of the scene,
Create the necessary environmental conditions for the operation of thee prrogram MR-JE-100B.
Depending on the way the field signals are generated,
The simulation debugging has two forms of hardware simulation and software simulation.
MR-JE-100B Operation manual/Instructions/Model selection sample download link:
/searchDownload.html?Search=MR-JE-100B&select=5