MITSUBISHI AD75P3 User's Manual PDF
Product model: AD75P3
Name: Positioning Module
Brand: MITSUBISHI
Sort: User's Manual
File language: English
2 axes.
2 axis linear interpolation, 2 axis arc interpolation.
Control unit: pulse, mm, inch, degree.
Determine the location of the number of data: 600/1 axis AD75P3 PDF.
Max output pulse: 400kpps (gap drive) /200kpps (open collector).
36 pin connector.
The working process of the input interface circuit: when the switch is closed, the diode light,
The transistor is then guided to the internal circuit and input signal under the irradiation of the light AD75P3
When the switch is off, the diode does not emit light, and the transistor is not on the way. Internal circuit input signal.
It is through the input interface circuit to the external switch signal into PLC internal can accept the digital signal AD75P3 PDF.
PLC selection with the development of PLC technology, more and more types of PLC products,
Function is becoming more and more perfect, and its application is more and more extensive.
Different series of different models of PLC has different performance, applicable occasions also have different emphasis,
Price also has a greater difference AD75P3 PDF. Therefore PLC selection,
Under the premise of meeting the control requirements,
Should consider the best performance to price ratio, a reasonable choice of PLC.
Input status and input information input from the input interface,
CPU will be stored in the working data memory or in the input image register MITSUBISHI User's Manual.
And then combine the data and the program with CPU.
The result is stored in the output image register or the working data memory,
And then output to the output interface, control the external drive MITSUBISHI User's Manual.
MITSUBISHI PLC is the main product in the production of MITSUBISHI motor in Dalian.
It uses a kind of programmable memory for its internal storage procedures,
Execute logic operation, sequence control, timing, counting and arithmetic operations, user oriented instruction,
And through digital or analog input / output control of various types of machinery or production process MITSUBISHI User's Manual.
DC input points: 64 points.
Innput voltage and current: 4/9mA, DC12/24V AD75P3 Manual.
Response time: 107ms.
Positive pole sharing.
16 point /1 a public side.
Output points: 64 points.
Output voltage and current: DC12/24V, 100mA/1 point, 2A/1 common end.
Response time: (2I/O update time * 5) Ms.
32 point /1 a public side.
Output form: transistor output, leakage type.
40 pin connector x 4.
Number of stations: 4 stops.
Compact remote I/O unit.
According to the control requirements of the system, using the appropriate design method to design MITSUBISHI PLC program.
Procedures to meet the requirements of system control as the main line,
Write one by one to achieve the control function or the sub task of the program,
Gradually improve the functions specified by the system.
MITSUBISHI PLC detection, fault diagnosis and display and other procedures.
These procedures are relatively independent, generally in the basic completion of the program design and then add.
Hardware simulation method is to use a number of hardware equipment to simulate the generation of the signal,
The signals are connected to the input end of the PLC system in a hard wired way,, and the timeliness is strong AD75P3 User's Manual.
Software simulation method is in the MITSUBISHI PLC in the preparation of a set of simulation program,
The simulation provides the field signal, which is simple and easy to operate, but it is not easy too guarantee the timeliness AD75P3 Manual.
Simulation of the process of debugging, debugging method can be used to segment, and the monitoring function of programmer.